A site survey is not a trip to "have a look at the site". The aim is to fix the assumptions about safety, equipment configuration and truck access.
Group 1 — energy demand
- Consumption by day, month and season.
- Base load, peak load and how fast the load changes.
- Pressure, temperature and gas quality at the delivery point.
- Target dates for commissioning and commercial operation.
Group 2 — site and traffic
- Coordinates, general layout drawing and levels.
- Gate size, turning radius, ground bearing capacity and internal roads.
- Proposed positions for tanks, skids, fencing and working areas.
- Vehicle flow, pedestrian flow and emergency access.
Group 3 — technical interfaces
- Piping diagram and existing tie-in points.
- Power supply, instrument air and interlock signals.
- Gas detection, fire-fighting and emergency shutdown systems.
- Who is responsible for operations on each shift.
A missing drawing does not always stop a project, but the gap must become an action item with an owner and a deadline. The danger is treating an assumption as a confirmed fact.
Before the survey date
Send the minimum file 48 hours ahead so the engineering team can prepare the list of points to measure and people to interview.